Reading a run from the downstream chamberMethod · in order
The order matters more than the kit: run it this way and the chainages can be found again.
-
Downstream cover first
Chamber 01
A survey starts at the lower chamber, not the gully everyone points at: that cover shows whether the run already stands full.
-
Gas test, then levels
Both ends
The chamber is gas-tested before anyone leans into it, and cover and invert levels are taken at both ends first.
-
In against the flow
Upstream travel
The camera travels upstream, so chainage counts up from a cover already lifted and nothing is referenced to a point nobody can reach.
-
Code it where it is
Clock reference
Chainage is read off the cable as it pays out, and each feature gets a clock reference — 12 the crown, 6 the invert — with a still.
-
Stop where the camera stops
Reported, not assumed
Where the camera stops, the report stops: the length beyond an obstruction goes down as unsurveyed against the chainage reached, never as sound.
Defect grading scheduleGrades 1–5
Everything hangs off the five rows below. A coded feature gets a grade; the grade decides which remedies are on the table; the remedy decides who countersigns. Structural and service condition are graded separately on the same run.
| Gr. | Condition recorded on the run | Sheet |
|---|---|---|
| 1 | Barrel round, joints closed, full bore to the next chamber. Nothing coded.Structural 1 · service 1 | Open |
|
||
| 2 | Hairline circumferential crack, slightly open joint, or deposits under five per cent of bore.CR · OJM · DES | Open |
|
||
| 3 | Multiple fractures, roots through a joint, deformation, or deposits five to twenty per cent of bore.FC · RI · D | Open |
|
||
| 4 | Broken pipe with pieces displaced, invert missing, a hard obstruction the camera cannot pass, or running infiltration.B · OB · IN | Open |
|
||
| 5 | Collapse. Bore lost, void over the crown, ground loss into the pipe, settlement at the surface.X · void confirmed | Open |
|
||
Note 1 · what the grade does not decideSched. note 1
A grade describes a length of pipe, not a job. The same code at the same grade is a two-hour patch under a driveway and a week of propping under a conservatory floor.
So the schedule is written before the quotation, with chainages, depth to invert and the surface above each defect.
Note 2 · fall, gradient and the slack runSched. note 2
A run that silts up every winter is usually not dirty. It is slack, and it was slack on the day it was laid.
Most settled deposits coded on a survey are a gradient fault: solids drop out of water that is not moving, and the bore narrows from the invert up.
Fall and gradient checker
Guide onlyEnter a length and a fall.
- Gradient
- —
- Reference gradient
- —
- Comparison
- —
The reference is Maguire’s rule — one in the bore in millimetres over 2.5 — a rule of thumb and nothing more. What a run is built to comes from the designer and the current approval documents.
Note 3 · where surface water is putSched. note 3
Surface water is the other half of the schedule.
Plenty of foul runs around Teynham carry roof water they were never sized for, because a downpipe went into a gully that turned out to be foul.
Which gully is which A tracer at the head of the run, watched at the next chamber, settles it.
Taking the roof off means putting it somewhere else: a soakaway, a crate, or a surface-water connection agreed first.
Order of preference Ground first, watercourse second, sewer last, and the sewer only on written agreement.
Whether the ground will take it is a question about the ground, not the roof.
Before the sheet means anything A pit to the depth of the soakaway, filled and timed three times, slowest used.
Soakaway sizing sheet
Guide onlyEnter a roof area.
- Inflow over the storm
- —
- Soaks away per metre run
- —
- Trench length needed
- —
- Storage to be held
- —
Worked for one duration and one trench shape: a metre wide, a metre deep, open-chambered. A real sizing repeats this across several durations and takes the worst, on the rate measured in the pit.
Note 4 · work carried out under 42990SIC 42990
The registered activity is civil engineering not elsewhere classified; here that means buried drainage, in four kinds of work.
-
Record
CCTV survey
A coded log against chainage, a still per feature, two grades. What a report must contain.
-
Remedy
Patch, line or dig
Three remedies, and conditions on the run that take the choice away. Which a defect allows.
-
New work
Laying a run
Set out upwards from the connection, bedded to a class, closed by test. Levels and bedding.
-
Submission
Sewer adoption
Drawings, levels and calculations that have to agree. What goes in.
Survey requests go to the office email, with a street address and the cover positions if known. The ground is on the Sittingbourne page; what is kept afterwards is in what the office holds.
Note 5 · the hole, the plant and the reinstatementSched. note 5
A drainage repair is mostly an excavation with a short piece of pipework in the middle. Utility records are pulled, the ground swept with a locator, trial holes dug by hand.
An opening in a public footway is a permitted street work with a reinstatement specification attached, not a patch of tarmac at the end of the day. One that fails inspection is dug up and done again at the opener's cost.
Soft ground is the same sequence in different materials, topsoil kept separate and put back last. How far the sides stand unsupported is a question about the ground around Sittingbourne.